In total 203 homes for social rent, shared equity, mid market and private sale will be built. Phase 1-28 homes for social rent. Phase 2- 87 homes for mid market rent. Phase 3 - 23 for social rent and 23 for shared equity
Project timescales
Work began on site March 2014 and Phase 1 completed in December 2015. Work began on Phase 2 in April 2015 and completed by September 2017. Work also started on Phase 3 in April 2016 and completed in September 2017.