A8 road resurfacing and Haymarket junction improvements
We are planning to carry out work in the Haymarket area over 5 days between 24 and 29 June from 19:30pm to 06:00am.
-
Update on Roseburn Terrace - May 2022
There have been some delays to work on Roseburn Terrace. This was due to finding asbestos under the pavement by the Roseburn Bar, damage to cellar ceilings and a corroded gas main.
-
CCWEL Update April 2022
Following the start of work earlier this year, we’re making good progress on the major new cycling and walking route linking the east and the west of the city centre.
-
Open for business campaign
Roseburn is still open for business
-
Watch our video about CCWEL
Join us at the launch of construction on the City Centre West to East Link
-
Roseburn Terrace footway works
We have recently found issues with the structures under the pavement on the south side of Roseburn Terrace.
-
Work begins on Section 2
We're starting work on Section 2 of the City Centre West East Link from Tuesday 1 March - Rosebery Cres to Manor Place.
-
Sending and receiving deliveries from Roseburn Terace
While the works for the CCWEL project are underway the loading and parking bays on Roseburn Terrace will be suspended for several weeks to allow for traffic management and safe access to the site.
-
Roseburn Terrace
If you are travelling in the Roseburn area, remember there is NO RIGHT TURN from Roseburn Terrace to Roseburn Street due to work being carried out.
-
Construction of CCWEL starts on 7 February in Roseburn Terrace
We are about to start work on a major new cycling and walking route linking the east and west of the city (including other improvements to the area)
-
Construction of the CCWEL starting soon
Construction is about to start week commencing 7 February 2022 in Roseburn.